Mortar Calculator — How Much Cement and Sand Do I Need?

Calculate the cement and sand needed for mortar. Covers bricklaying, blockwork, pointing, and rendering with standard UK mix ratios.

Choose how to specify the quantity

Total wall area to be covered

Different applications use different mortar rates

1:4 is standard for most domestic work

Material Prices (optional)

How We Calculate This

This calculator determines the volume of mortar needed, then breaks it down into cement and sand quantities based on your chosen mix ratio.

Mortar rates by application

  • Bricklaying (half-brick): 0.03 m³ mortar per m² (~1kg per brick)
  • Bricklaying (full-brick): 0.06 m³ mortar per m²
  • Blockwork: 0.012 m³ mortar per m² (~1.5kg per block)
  • Pointing/repointing: 0.01 m³ mortar per m²
  • Rendering (15mm coat): 0.015 m³ mortar per m²

Mix ratio material quantities

Per cubic metre of mortar:

  • 1:3 (strong): ~12 bags cement (25kg), ~1.5 tonnes building sand
  • 1:4 (general): ~9 bags cement (25kg), ~1.5 tonnes building sand
  • 1:5 (internal): ~7 bags cement (25kg), ~1.5 tonnes building sand

Standards

Mortar should comply with BS EN 998-2 (Specification for mortar for masonry). Mortar designation should be selected based on exposure conditions per BS 5628 / PD 6697. General-purpose mortar (M4) is suitable for most domestic applications.

Frequently Asked Questions

Last updated: February 2026

All calculations are estimates. Verify with your supplier.